skip navigation
Arizona Department of Transportation
 
  Site Index
 
About Flagstaff District

Inside Flagstaff District

Project Information

Employment

Environment

Other Districts

Links



Flagstaff District Home Page
Arizona Travel Information Travel Info AZ511.gov
Adopt a Highway Program Adopt a Highway Program
U.S. 2010 Census - 2010.census.gov


Current Flagstaff Projects

I-40 Walnut Canyon Westbound

  Project No.: 40 CN 205 H545701C ARRA-040-E(202)A
  Location:

Project is westbound only from MP 209.1 to MP 205.1. The Cosnino Interchange is located within this project.

  Contractor: C.S.&W. Contractors, Inc.
  Programmed Cost: $5,809,917.48
  Scope:

Reprofile the vertical curves. This involves taking out some of the small grades.

  Expected Project
Duration:
Project will run into the fall of 2009 at which time it will stop. It will be resumed and completed Spring 2010.
  News Release:

ADOT to close westbound I-40 ramps at Cosnino Road ~ June 24, 2009

     
McGuireville Rest Area – Yavapai County Line S/B
  Project No.: 017-YV 296 H613601C IM-017-B(008)A
  Location:
McGuireville Rest Area, and the south bound lanes from the Yavapai County Line to the rest area.
  Contractor: Fisher Sand & Gravel Co. dba Southwest Asphalt Paving
  Programmed Cost: $6,333,333
  Scope:
Make waste water system improvements at the McGuireville rest area; mill and replace the existing asphalt and apply friction course from the county line to the rest area.
  Expected Project
Duration:

Fall 2009 to Summer 2010

     
SR 89A Continuous Highway Lighting
  Project No.: 89A YV 371 H7130 01D, HES A89-B(202)
  Location: SR 89A from milepost 371 to 373
  Contractor: Not bid yet
  Programmed Cost: Current estimate $2,000,000
  Scope: Install continuous highway lighting and traffic signal at Andante.
  Expected Project Duration: Projected for Fall 2010 to Spring 2011
  Project Documents: Sedona Pedestrian Crossing Study
    Highway Enhancements for Safety Report
    Funding Approval
    Revised Funding Approval
    Final Project Assessment
    Final Lighting Design Criteria Report
    Presentation to Sedona City Council October 28, 2009
    Public Information Packet on Lighting System Alternatives
    Public Comment Form
    Information on Nighttime Lighting
     
SR 179 Village of Oak Creek to Y (Project 1 and 2)
  Project No.: STP-TEA-A(001)B and STP-TEA-A(002)B
  Location:
Project 1 is from MP 304.5 (1 mile south of Village of Oak Creek) to MP 310.4 (Back o’ Beyond) and Project 2 is from MP 310.4 to 313.4 (the “Y”) in the City of Sedona.
  Contractor: Southwest Asphalt Paving (Project 1)
  Programmed Cost: Project 1 $36,114,000
Project 2 $51,750,000
  Scope:
Projects consist of complete rebuild of highway to a multimodal, two lane parkway.
  Expected Project Duration: Project 1 Completed
Project 2 Spring 2008 to Spring 2010
     

Documents are posted as they become available in PDF format, which requires Adobe Reader to view.

Privacy Statement | Contact ADOT
© Copyright Arizona Department of Transportation. All Rights Reserved